Construction on the New Chemistry Building, Lot 3 Closed April 1-3

New Chemistry Building construction, as of March 27, 2019, with equipment in the foreground.

New Chemistry Building construction, as of March 27, 2019.

New Chemistry Building Activity

The great weather in Athens has allowed the work to continue at a good pace. This week and next drilled pier installation will continue.

March 25, 2019

  • Waterline Installation/Testing – Note, rework under the Southern sidewalk at South Green Drive is required. No impact to traffic is anticipated.
  • Continue drilled pier installation.
  • Begin layout for foundations.

April 1, 2019

  • Waterline Installation/Testing – Note, rework under the southern sidewalk at South Green Drive is required. No impact to traffic is anticipated.
  • Continue drilled pier installation.
  • Begin foundation installation.
  • Install Helium Line under University Terrace – Note, Lot #3 is planned to be shutdown on April 1-3.