Scheduled activity for the new Chemistry Building during the weeks of Jan. 7 and Jan. 14.
Jan. 7
- Continue installation of Sanitary and Storm piping and structures. Involves deep excavations, backfill and compaction of soil, hauling/trucking on and off site.
- Install Sanitary line to Surface Science Lab. NOTE – Tentatively, Pedestrian Access to Surface Science will be shutdown Thursday from 8-12pm.
- Perform testing of Sanitary Lines. NOTE – This will require a ramp on the multi-modal pathway.
Jan. 14
- Continue installation of Sanitary and Storm piping and structures. Involves deep excavations, backfill and compaction of soil, hauling/trucking on and off site.
- Perform testing of Sanitary lines.
- Continue building pad prep. Involves moving/grading soil.
- Gas Line Phase 2 Installation